Recent indexed payments
Up to 100 recent indexed payment rows are shown on this page.
| Date | Invoice | Description | Amount |
|---|---|---|---|
| February 5, 2015 | RETENTION | FINAL PAYMENT DUE ON CONSTRUCTION OF H & W FACILITY RETENTION | $30,000.00 |
| May 5, 2014 | 21456 | Check total. This register lists checks only. | $141,547.20 |
| April 8, 2014 | 21287 | Check total. This register lists checks only. | $30,462.00 |
| December 12, 2013 | 20696 | Check total. This register lists checks only. | $34,790.00 |
| June 6, 2013 | 19491 | Check total. This register lists checks only. | $139,324.12 |
| March 7, 2013 | 18863 | Check total. This register lists checks only. | $1,235,250.39 |
| December 19, 2012 | 18355 | Check total. This register lists checks only. | $563,740.96 |
| December 13, 2012 | 18302 | Check total. This register lists checks only. | $384,838.54 |
| November 29, 2012 | 4072 | — | $299,377.44 |
| November 29, 2012 | 4051 | — | $2,007.00 |
| November 1, 2012 | 4071 | — | $781,753.53 |
| September 10, 2012 | 4070 app14 | — | $1,465,968.32 |
| August 2, 2012 | 13 | — | $1,127,134.13 |
| June 21, 2012 | 4029 | permit water solar system | $185.00 |
| June 21, 2012 | 4024 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR WITH 15% CONTINGEN Pages: 22 of 42 Thursday, July 05, 2012 | $397,929.22 |
| May 17, 2012 | 3994 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR BILLING (11) | $429,107.69 |
| May 17, 2012 | 3990 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS APRIL BILLING 2012 | $620,019.73 |
| May 17, 2012 | 3939 | REIMB ENCHROACHMENT PERMIT 2012-044 | $894.60 |
| May 17, 2012 | 3940 | PUBLIC IMPROVEMENT PERMIT 2012-041 HEALTH/WELLNESS | $12,920.00 |
| May 3, 2012 | 3682 | CARPET REPAIR CARL MAY PROJECT | $181.00 |
| May 3, 2012 | 3681 | CARPET REPAIR CARL MAY PROJECT | $1,629.00 |
| April 26, 2012 | 3942 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR WITH 15% CONTINGEN | $841,615.98 |
| March 27, 2012 | 3884 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR WITH 15% CONTINGEN | $361,029.10 |
| February 23, 2012 | 3836 | CONSTRUCTION CONTRACT COM | $501,338.21 |
| February 2, 2012 | 3796 | CONSTRUCTION CONTRACT COM | $164,773.03 |
| December 21, 2011 | 3763 | — | $802,159.37 |
| November 17, 2011 | 3738 | — | $496,234.46 |
| November 9, 2011 | 3692 | — | $273,423.56 |
| September 22, 2011 | 3671 | CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR WITH 15% CONTINGEN | $642,606.01 |
| September 14, 2011 | 3639 | CARL MAY ADDITIONAL CONDUITS FOR ELECTRONIC SOUND SYSTEMS 2011 | $157.95 |
| September 14, 2011 | 3638 | CARL MAY ADDITIONAL CONDUITS FOR ELECTRONIC SOUND SYSTEMS | $1,421.56 |
| September 1, 2011 | 3625 | CONSTRUCTION CONTRACT & DIAS CONSTRUCTION CARL MAY | $119,000.00 |
| June 16, 2011 | 1000 | REIMB BUILDING PERMIT COSTS CARL MAY REHAB | $2,845.79 |
Source records
- Payment Register 3/1/2012..3/31/2012 - 2012-05-01 — page 30 (City of Desert Hot Springs) Source date: May 1, 2012. Validated import citation. Import/review method: authenticated agent import.
Supporting excerpt
16591 2012-03-27 DOUG WALL CONSTRUCTION, INC CONSTRUCTION CONTRACT COM HEALTH/WELLNESS CTR WITH 15% CONTINGEN $361,029.10