Fire Station 98

Design and construction of a new fully operational fire station on Hacienda Avenue at Long Canyon Drive.

Project number
8004
Department
Public Works
Status
completed
Original budget
$8,052,000.00
Current budget
$8,857,200.00
Indexed payment total
No payment records indexed; actual paid unknown
Completion date
September 22, 2025

Overview

Design and construction of a new fully operational fire station on Hacienda Avenue at Long Canyon Drive.

Contracts

Contracts currently indexed
ContractVendor / projectAward dateAuthorized
Construction AgreementOakview Constructors Inc.March 19, 2024$8,424,506.00

Source records

  1. City Council - January 20, 2026 - Action Minutes — page 17 (City of Desert Hot Springs) Source date: January 20, 2026. Human-reviewed citation.

    Original source file or public URL is not attached. The link above opens the indexed source metadata.

    Import/review method: review queue.
    Supporting excerpt
    The Fire Station No. 98 project was substantially completed September 22, 2025. The approved construction amount was $8,052,000 with a 10% contingency of $805,200, for a total project budget of $8,857,200.